| Owner
/ Client / Consultants |
Projects |
|
NEM-MHS, The Netherlands |
|
4Nos.HRSGsat Layyah
Power Station Desalination Plant Extension- Sharjah Electricity & Water
Authority - Fabrication of stacks, ducts and structures
& Mechanical
erection, piping erection and electrical
& instrumentation works.
|
|
|
G + H Schallschutz., Germany
|
GT13E2 Az Zour Project, Kuwait
Supply, fabrication, surface preparation and
insulation of Exhaust Gas System
– 3 Units
|
|
Siemens Germany.
|
Taweelah New B Extension,
Abu Dhabi, U.A.E.- Erection of Fuel Storage
Tanks - 2 Nos. 40 M dia x 16 M ht.
|
Alstom Power Centrales
France.
|
Combined Cycle Power Plant
for Dubai Aluminium Co., Dubai. U.A.E-Mechanical
and Electrical Erection Work – Installation of Gas
Turbine & GT
Generator, Steam Turbine& ST Generator, Power Island
& Rest of
Plant.
|
|
G + H
Schallschutz
Germany /
Siemens Power Generation, Germany
|
Al Aweer Phase–III Project – DEWA, UAE -Supply &
fabrication of Exhaust Gas Stack – 4 Nos. Approx. Weight :
360 Ton
Taweelah New B Extension Project, U.A.E.-Supply,
fabrication and erection of Exhaust Gas Stack–2Nos.,
Exhuast Gas Diffuser–3 Nos. Approx. Weight : 550 Tons
|
Toshiba Corporation,
Japan /Lahmeyer International
|
Dubai Electricity and Water Authorities (DEWA)-
Jebel Ali L Station–Phase – 1
Prefabrication of
Pipe spools for steam piping
- 625.551
M.T.
Design, Engineering, supply and erection of
Tanks – 7 nos.
Fuel Oil
(CS)
30.5 M Dia x 14.2 M Ht
8500 m3 – 4 nos.
D M Water (SS 316L)
14.0 M Dia x 11.2 M Ht 1500 m3 - 2 nos.
Distilled Water (SS 316 L) 5.2 M dia x 6.4 M ht
– 100 m3 -
1 no.
(Carbon Steel 1000 M.T & SS 316L 200 MT)
|
Toshiba Corporation,
Japan /
Lahmeyer International
|
•Design,
supply, fabrication, surface treatment and
delivery of ASME Code ”U” stamped Carbon
Steel Air Receiver Tanks – 4 nos. 36.0 Cu.M.
capacity -
2.35 M dia x 10 M overall height x 16 mm
thick - Material – SA 516 Gr. 70
Internal design
pressure 13 bar g -
temp 600c
•Design,
drawing, fabrication , surface treatment
& delivery of : i)
Carbon Steel Tanks – S275 JR
-
6 nos. sizes varying 1200 to 2200
mm dia.
Height 2300 mm to 3620 mm
cap. – 2000 ltrs to 27000 ltrs.
ii)
False start drain tank – 3
nos.Slope diesel fuel tank – 1 no.
|
|
Alstom Power
Environment Control Systems, Norway |
FCC Seawater Scrubber Project - Yanbu
- Fabrication of stack support structures and ducts -
105 tons. |
|
G + H Schallschutz, Germany |
Al Aweer Power Plant, Dubai, U.A.E
- Supply and fabrication of 3 Nos.
Exhaust Systems. |
|
GOWA Gmbh & Co. Germany |
Sohar Power Station, Oman -
Supply & fabrication of 3
nos. Silencer Casing
|
|
Enersul Limited Partnership, Canada |
Dolphin Energy Limited - Qatar
- Supply & fabrication
of Structural Steel for Upstream & Compression facility. |
|
IHI
UAE Co. Ltd. Abu Dhabi/ Toshiba Japan |
Jebel Ali L Station & Umm Al Nar WPP -
Design,
drawing, fabrication , surface treatment and
delivery of 7 nos.
Tanks.&
Prefabrication of Pipe spools - 1200 M.T
|
|
Toshiba
Corporation, Japan |
Jebel Ali
Power & Desalination Station ‘L’ Phase 1 Project – DEWA
-
Design,
supply and erection of Tanks – 7 nos.
Fuel Oil
Storage Tanks-4 nos. (CS),D M
Water Tanks - 2 nos. (SS 316 L),
Distilled Water Tank - 1 no. (SS 316 L) |
|
Nooter / Eriksen.Italy |
Al Shuweihat S1 combined cycle Power & Desalination Plant –
CMS Power Company – Client – Siemens - Supply and fabrication of
Secondary
Structures – 5 Units.
Distribution Grids -5 units,Piping
Supports -5 units,Atmospheric
Blow Off tanks – 5 nos. – ASME Code stamped,
Upper &
Lower Gas Baffles - 5 units.
Stainless
steel turning vanes – 5 units
|
|
G + H
Schallschutz, Germany
|
Al Shuweihat S1 combined cycle Power &
Desalination Plant -
CMS Power Company–Client–Siemens- Supply, fabrication, insulation and erection of 2 Nos.
Exhaust Gas System |
|
Dubai
Electricity & Water Authority.
Fitchner / Enelpower
Dodsal Pte Ltd. |
Jebel Ali Power and Desalination Station
‘K’ – Phase II
i)
Fabrication and erection of WHRB Stacks - 3 nos.
7.5 M dia x 60 M ht Material Corton Steel
ii) Blasting, Prime, Intermediate & finishing painting of Piping work |