Activity ID
Activity Description
Orig Durin Hr
% Comp
SD13990 Repairs/re-radiography if any outlet joint later 48 100
SD14000 Install All Dismantled kiln airlines 72 100
SD18000 Refractory Installation inside klin by FCI 168 100
       
Resource/cost Profile Legend
Resource :CR500
Total early usage per Day(current estimate)
____________________ Scheduled budget curve
Detail Scale (left) : HR
Cumulative Scale (right): 10HR
Project start 05Dec98 8.00
Project Finish 04Apr99 22.59
Data date 31Mar99 23.00
Run date 30Jul00 12.00


© Primavera Systems, Inc
Target Bar
Early Bar
Float Bar
Progress Bar
Critical Activity
Petron Emirates Contracting Co.(LLC)
Job Schedule for Klin Shutdown
Classic Schedule Layout