|
Activity
ID
|
Activity
Description
|
Orig
Durin Hr
|
![]() |
|
| SD13990 | Repairs/re-radiography if any outlet joint later | 48 | 100 | |
| SD14000 | Install All Dismantled kiln airlines | 72 | 100 | |
| SD18000 | Refractory Installation inside klin by FCI | 168 | 100 | |
| Resource/cost Profile Legend | ||||
| Resource
:CR500 Total early usage per Day(current estimate) ____________________ Scheduled budget curve Detail Scale (left) : HR Cumulative Scale (right): 10HR |
||||
|
Project
start 05Dec98 8.00
Project Finish 04Apr99 22.59 Data date 31Mar99 23.00 Run date 30Jul00 12.00 © Primavera Systems, Inc |
![]() |
Target
Bar
Early Bar Float Bar Progress Bar Critical Activity |
Petron
Emirates Contracting Co.(LLC)
Job Schedule for Klin Shutdown Classic Schedule Layout |
|